| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 3 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Abh SamrddhiLapsed · completion date passed | B V TARAKESHWARI | Plot | ~940–1,200 sqft (estimate: filed carpet plus 25%) | Feb 2026 |
| Arohana SerenityCompleted (regulator flag) | Nagaraja B | Plot | ~570–1,790 sqft (estimate: filed carpet plus 25%) | Completed |
| Byraveshwara LayoutLapsed · completion date passed | Channappa and Puttalakshmamma | Plot | ~800–1,500 sqft (estimate: filed carpet plus 25%) | Dec 2024 |
| Cm1 Lakh Multi Storey Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 334 sqft carpet (as filed) | Feb 2025 |
| DS Max SamyakActive · 100% built | DS-Max Properties | Apartment | 761–1,078 sqft | Jan 2028 |
| Ds Max Star NestCompleted · OC 04-04-2020 | K V SATISH | Apartment |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 9 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Location & risks | – | – | – | – |
|---|
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | 1 | – | Review |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| – |
| Completed |
| Ds-Max Sky SupremeCompleted · OC 29-11-2023 | DS- Max Properties Private Limited | Apartment | – | Completed |
| Guru Punvaanii EterniaCompleted (regulator flag) | Guru Punvaanii Infra LLP | Plot | ~800–1,860 sqft (estimate: filed carpet plus 25%) | Completed |
8 of 36 other projects in Kengeri, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Kommaghatta NPKL Phase-3 in the interactive atlas
Approval or registration
Building plan sanctioned
BDA · plan 5/Housing/P/01/2019/2020
K-RERA filing, approvals
Approval or registration
Khata issued
A Khatha · NA · Survey 115/1
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1251/310/PR/111124/007211
K-RERA registration ·
Approval or registrationThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Charges on the land | Not verified yet | |
|---|---|---|
| Developer's project loan | None declared | |
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: Survey Sketch, 1 page, English.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 115/1 | |
|---|---|---|
| Land extent, Sy 115/1 | 3 ACRES 07 GUNTAS | |
| Area on the KGIS map | Not verified yet | |
| Land area of this registration | 12,848 sq m | |
| Khata | A Khatha · NA · 5 Mar 2024 | |
| Building plan (BDA) | Sanctioned 12 Jun 2019 · No. 5/Housing/P/01/2019/2020 | |
|---|---|---|
| Power NOC (BESCOM) | Not verified yet | |
| Fire NOC | KSFES/NOC/74/2017 | Clear |
| Environmental clearance | SEIAA 26 CON 2017 · issued 28 Apr 2017 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 30 Jul 2024 |
| Land conversion | Declared not converted | |
|---|---|---|
| Survey numbers | 115/1 |
₹99 for this report opens Disputes & cases for this project, yours to read for good.
2BHK · avg 75 m² 100%
| Type | Flats | Carpet per flat, average (sq ft) |
|---|---|---|
| 2BHK | 336 | 809 |
| Good Earth Ochre | about 3 km | Locked | |
|---|---|---|---|
| Good Earth Cadence | about 3.5 km | Locked | |
| Samaya Sunshine | about 4 km | Locked | |
| Sumadhura Pramoda | about 5 km | Locked | |
| Sobha Royal Crest | about 7.5 km | Locked |
| Kommaghatta NPKL Phase-3 This project | This project is the point the others are measured from | 30 Jul 2024 | Not filed | Not verified yet |
|---|---|---|---|---|
| Good Earth Ochre | about 3 km | 31 Oct 2027 | 92% (35 of 38) | Locked |
| Good Earth Cadence | about 3.5 km | 31 Dec 2028 | 72% (104 of 145) | Locked |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Not verified yet | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | about 3 km, Kengeri Yellamma temple | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Amenities declared | Electricity · CCTV Surveillance · Power Backup | |
|---|---|---|
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.00 (336 covered spaces for 336 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
Ten-year July mean for this taluk: 23.2 m
Across Bengaluru South, the water table sat 16.9 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 23.2 m, and it fell 4.2 m over the year.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 16.9 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, BWSSB | |
| Nearest city water main | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 30 Jun 2023 | |
| RERA completion date | 30 Jul 2024 | |
| Work began, as filed | 24 Aug 2016 | |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | filed: H 41 m, I 40 m, J 40 m | |
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Provided, 10 sq m | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Not verified yet | |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | KSFES/NOC/74/2017 | |
| Environmental clearance | SEIAA 26 CON 2017 · issued 28 Apr 2017 | |
| Architect's certificate, registration | Site inspected 21 Mar 2024 | |
Land · ₹19.09 Cr 11.6%Development · ₹146.00 Cr 88.4%
| Estimated cost | ₹165.08 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹122.51 Cr | |
| Estimated cost, chartered accountant's certificate | ₹165.08 Cr, same as the filing | |
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
| Escrow bank | Canara Bank · BDA COMPLEX COMPOUND, PB NO 2019SANKEY ROAD K P WEST, BANGALORE | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| K-RERA registrations under this promoter | 15 | |
|---|---|---|
| Marked completed | 4 | |
| Past promised date, not completed | 9 | Review |
| Revoked or withdrawn | 2 | |
| Complaints filed against the promoter | 45 |
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan (BDA) | Sanctioned 12 Jun 2019 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | Canara Bank · BDA COMPLEX COMPOUND, PB NO 2019SANKEY ROAD K P WEST, BANGALORE | |
| Garden Square | about 9 km | Locked |
|---|
| Jhanavi Trishul Alaska | about 9.5 km | Locked |
|---|
| Song Of Wind | about 10 km | Locked |
|---|
| Srivara Vasudha | about 10 km | Locked |
|---|
| Mahindra Eden Phase-2 | about 10 km | Locked |
|---|
| Axis Amarissa | about 11 km | Locked |
|---|
| Adarsh Premia | about 11 km | Locked |
|---|
| about 4 km |
| 31 Dec 2026 |
| 33% (8 of 24) |
| Locked |
| Sumadhura Pramoda | about 5 km | 31 Dec 2029 | 50% (148 of 297) | Locked |
|---|
| Sobha Royal Crest | about 7.5 km | 31 Dec 2028 | 100% (329 of 329) | Locked |
|---|
| Garden Square | about 9 km | 30 Jun 2026 | 84% (193 of 230) | Locked |
|---|
| Projects within 4 km, counted | 18 (18 with an approximate location) | |
|---|---|---|
| Flats in them | 3,815 | |
| Booked | 1,888 of 3,815 (49%) | |
| Unsold | 1,927 | |
| Booked a month, pooled | 35 flats | |
| Months to sell, pooled | 56 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | about 0.5 km, tertiary drain | |
| Ground level | Not verified yet | |
| Metro, operational | about 1.5 km, Kengeri | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 41.5 |
| MG Road (CBD) | 16.5 |
| Manyata Tech Park | 22.5 |
| ITPL, Whitefield | 31 |
| Ecospace, Bellandur ORR | 23.5 |
| Electronic City Ph 1 | 24.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 1 km, named STP-5 on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | about 2 km, named Hindu Crematorium on OpenStreetMap | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |