Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Value & LTV
3BHK A
Not verified yet
Calculation
Not verified yet
Conditions
Collateral checks
Data room
Documents filed for this project
Documents filed260On K-RERA
Available23892% of filed
K-RERA only22
Approvals with a validity date1Valid today
Approvals & NOCs
What we read
Pollution board consentValid until 4 Jul 2029Issued 5 Jul 2024
Environmental clearanceIssued 8 May 2024Filed as SEIAA, p. 1
Fire NOCIssued 27 Nov 2023Filed as Fire Force NOC, p. 1
Available
K-RERA only
Available
1 pageAvailable
2 pagesAvailable
1 pageAvailable
K-RERA only
K-RERA only
K-RERA only
6 pagesAvailable
9 pages3 factsAvailable
3 factsK-RERA only
2 pagesAvailable
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
Filed 31 Aug 20241 pageAvailable
Filed 31 Aug 20241 pageAvailable
Filed 31 Aug 20243 pagesAvailable
Filed 31 Aug 202442 pages2 factsAvailable
Filed 31 Aug 20241 pageAvailable
Source: K-RERA project page and the documents filed there, as read by us. 67 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Unlock this full report₹99 for this report · opens Contract & costs, Title & ownership and Disputes & casesUnlock
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Bren Avaana in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Not verified yet
Survey sketch
Survey sketch filed with K-RERA
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
about 6 km, Mantri Lake view Appartment Next to Talagattapura Lake
Height above nearest drain
Not verified yet
Flooding
Site vs nearest drain
Nearest storm drain
about 0.5 km, tertiary drain
Nearest lake, tank or pond
about 0.5 km, an unnamed tank
Height above nearest drain
Not verified yet
Drains and lakes around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Electricity · CCTV Surveillance · Community Hall · Indoor Sports facility · Gym · Power Backup · Water and Sanitation
Club House, built
0%
Electricity, built
0%
Outdoor Sports facility, built
0%
Swimming Pool, built
0%
Parks, built
0%
Water and Sanitation, built
0%
Kitchen handover
Not verified yet
Covered parking per unit
1.00 (327 covered spaces for 327 units)
Sewage plant
Not verified yet
Power backup
Declared by the promoter
Around it
Water
Groundwater, Bengaluru South taluk average
Ten-year July mean for this taluk: 23.2 m
Across Bengaluru South, the water table sat 16.9 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 23.2 m, and it fell 4.2 m over the year.
Water at a glance
Groundwater
Bengaluru South taluk average, July 2023: 16.9 m below ground
What it means
Not verified yet
Water below ground
16.9 m, the taluk average
Through the year
Not verified yet
Water supply, as filed
Borewell
Nearest city water main
Not verified yet
Distances
Within 3 km of the filed pin
Connectivity
Straight-line distance from the site
Nuisances
Distance from the filed pin
DOSL nuisance layer
Landfill or waste transfer station
None within 3 km
Completion, as the promoter reported it
As the promoter reported it
Site photos filed with K-RERA, Q2 2026-27
Work left
By component, Q2 2026-27
Quarterly return, Q2 2026-27
Main structure
30% · planned by 11 Mar 2026
Electrical and plumbing finishing
Not started · planned by 15 May 2027
Internal roads
Not verified yet
Club house
Not started
Completion
20%
Completion, accountant
Not verified yet
Dates
Dates
Filed dates
Possession, agreement
Not verified yet
Schedule end
14 Jul 2027
RERA completion date
29 Feb 2028
Completion date, agreement
29 Feb 2028
Work began, as filed
29 Jul 2024
Specified structure
What the promoter specified · not an inspection
Structure
RCC structure, Mivan aluminium formwork
Foundation
Not verified yet
Wall material
Not verified yet
Wall thickness
Not verified yet
Concrete / steel grade
Not verified yet
Building heights, fire NOC
75.33 m filed, 3 towers
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot