Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Value & LTV
3BHK A
Not verified yet
Calculation
Not verified yet
Conditions
Collateral checks
Data room
Documents filed for this project
Documents filed166On K-RERA
Available166100% of filed
K-RERA only0
Approvals with a validity dateNone read
Approvals & NOCs
What we read
Water and sewerage NOC (BWSSB)Issued 27 Oct 2022Filed as Bwssb noc, p. 1
Available
Available
Available
Available
Available
Available
Available
Available
Available
1 pageAvailable
Available
Available
Available
Available
Available
Available
Available
Available
Filed 16 Apr 20228 pagesAvailable
Filed 14 May 2022Available
Filed 6 Jun 20222 pagesAvailable
Filed 24 Jun 20222 pagesAvailable
Filed 24 Jun 20221 pageAvailable
Filed 16 Jul 20222 pagesAvailable
Filed 16 Jul 20221 pageAvailable
Filed 16 Jul 20221 pageAvailable
Filed 8 Nov 20222 pages1 factAvailable
Filed 8 Nov 20221 pageAvailable
Filed 8 Nov 20221 pageAvailable
3 pagesAvailable
1 pageAvailable
2 pagesAvailable
2 pagesAvailable
2 pagesAvailable
Source: K-RERA project page and the documents filed there, as read by us. 19 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Unlock this full report₹99 for this report · opens Title & ownership and Disputes & casesUnlock
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
Metro station
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Dharani Greens in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Not verified yet
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Title & ownership and Disputes & cases for this project, yours to read for good.
Power lines, drains and flood locations around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Storm drain, primary
Storm drain, smaller
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Drains, lakes and flood locations around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, primary
Storm drain, smaller
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Electricity · CCTV Surveillance · Power Backup · Water and Sanitation
Kitchen handover
Not verified yet
Covered parking per unit
1.00 (19 covered spaces for 19 units)
Sewage plant
Not verified yet
Power backup
Declared by the promoter
Around it
Water
Groundwater, Yelahanka taluk average
Ten-year July mean for this taluk: 32.6 m
Across Yelahanka, the water table sat 11.4 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 32.6 m, and it recovered 9 m over the year.
Water at a glance
Groundwater
Yelahanka taluk average, July 2023: 11.4 m below ground
What it means
Not verified yet
Water below ground
11.4 m, the taluk average
Through the year
Not verified yet
Water supply, as filed
Borewell
Nearest city water main
Not verified yet
Distances
Within 3 km of the filed pin
Connectivity
Straight-line distance from the site
Nuisances
Distance from the filed pin
Completed
Quarterly return
Main structure
Not verified yet
Electrical and plumbing finishing
Not verified yet
Internal roads
Not verified yet
Club house
Not verified yet
Completion
Completed, occupancy certificate 20 Sep 2023
Completion, accountant
Not verified yet
Dates
Dates
Filed dates
Possession, agreement
Not verified yet
Schedule end
15 Aug 2024
RERA completion date
1 Oct 2024
Work began, as filed
1 Oct 2021
Specified structure
What the promoter specified · not an inspection
Structure
Not verified yet
Foundation
Not verified yet
Wall material
Not verified yet
Wall thickness
Not verified yet
Concrete / steel grade
Not verified yet
Building heights, fire NOC
11 m filed
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
Metro station
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot