As of 27 Oct 2026
Builder · Bengaluru · Category B
Vajram Group
- Projects tracked
- 5
- 5 hand-researched
- RERA registrations
- 6
- 2 completed
- Overdue share
- 17%
- past latest filed completion
- Average slip
- 20 mo
- promised vs post-extension
Vajram Group has 5 residential projects in the DOSL corpus, concentrated in Thanisandra, Yelahanka. 5 carry hand-researched pricing and diligence notes; the rest are traced from Karnataka RERA registrations.
Across every registration Vajram Group has filed with Karnataka RERA (6 in total, merged across the promoter's SPVs and alias spellings), 2 are recorded complete and 1 are past their latest filed completion date, an overdue share of 17%, with an average schedule slip of 20 months.
The promoter has been registering projects since 2014-07-14, most recently in 2025-10-24, covering 762 units in total.
Disputes & cases
Court cases on Vajram Group and its land, and buyer complaints on its other projects, are in each project's full report, under Disputes & cases. Open a report from the project list below.
Where Vajram Group builds
All 5 Vajram Group projects
Median builder quote across those with a published price: ₹10,417/sqft.
| Vajram Codename Te AmoLaunched | Yelahanka | Apartment | 2,238–2,628 sqft | ₹10,417/sqft | 2029 | 74 B+ |
| Vajram ElinaReady to move | Thanisandra | Apartment | 1,200–1,500 sqft | ₹9,850–10,950/sqft | Jul 2018 | 78 A |
| Vajram NewtownReady to move | Thanisandra | Apartment | 1,250–1,860 sqft | ₹10,000–13,650/sqft | Completed | 61 B |
| Vajram Newtown 2.0Under construction | Thanisandra | Apartment | 1,192–1,600 sqft | ₹9,300–9,900/sqft | Jan 2028 | 73 B+ |
| Vajram ViveraUnder construction | Yelahanka | Apartment | 1,573–2,406 sqft | ₹14,200–14,800/sqft | Feb 2030 | 75 A |
Vajram Group: common questions
- Does Vajram Group deliver on time?
- Across 6 Karnataka RERA registrations, 1 are past their latest filed completion date, an overdue share of 17%, with an average slip of 20 months between the completion date first promised and the one after extensions. For context, the median overdue share among Bengaluru's curated Category-A builders is around 38% and the weighted-median slip is roughly 21 months, so schedule slip is the market norm rather than the exception.
- How many projects does Vajram Group have in Bengaluru?
- 5 are tracked here, across 2 localities including Thanisandra, Yelahanka. Each has its own page, and its own full report with the filed schedule, unit mix, land schedule and unsold-inventory trend.
Track-record figures are computed from Vajram Group’s own Karnataka RERA filings, merged across the promoter’s SPVs and alias spellings.