As of 27 Oct 2026
Builder · Bengaluru · Category B
GM Infinite
- Projects tracked
- 5
- 5 hand-researched
- RERA registrations
- 8
- 0 completed
- Overdue share
- 88%
- past latest filed completion
- Average slip
- 30 mo
- promised vs post-extension
GM Infinite has 5 residential projects in the DOSL corpus, concentrated in Electronic City. 5 carry hand-researched pricing and diligence notes; the rest are traced from Karnataka RERA registrations.
Across every registration GM Infinite has filed with Karnataka RERA (8 in total, merged across the promoter's SPVs and alias spellings), 0 are recorded complete and 7 are past their latest filed completion date, an overdue share of 88%, with an average schedule slip of 30 months.
The promoter has been registering projects since 2012-02-28, most recently in 2019-04-05, covering 0 units in total.
Disputes & cases
Court cases on GM Infinite and its land, and buyer complaints on its other projects, are in each project's full report, under Disputes & cases. Open a report from the project list below.
Where GM Infinite builds
All 5 GM Infinite projects
Median builder quote across those with a published price: ₹6,400/sqft.
| GM Ambitious EnclaveReady to move | Electronic City | Apartment | 495–990 sqft | ₹6,000–6,800/sqft | Completed | 47 C |
| GM Global Techies TownReady to move | Electronic City | Apartment | 904–1,755 sqft | ₹8,350–9,500/sqft | Completed | 58 B |
| GM Infinite E-City TownReady to move | Electronic City | Apartment | 900–1,507 sqft | ₹5,100–5,600/sqft | Completed | 65 B+ |
| GM Orchid EnclaveReady to move | Electronic City | Apartment | 350–990 sqft | ₹5,000–6,000/sqft | Completed | 57 B |
| GM TownsvilleReady to move | Electronic City | Rowhouse | 3,358–4,300 sqft | ₹9,180–9,530/sqft | Completed | 47 C |
GM Infinite: common questions
- Does GM Infinite deliver on time?
- Across 8 Karnataka RERA registrations, 7 are past their latest filed completion date, an overdue share of 88%, with an average slip of 30 months between the completion date first promised and the one after extensions. For context, the median overdue share among Bengaluru's curated Category-A builders is around 38% and the weighted-median slip is roughly 21 months, so schedule slip is the market norm rather than the exception.
- How many projects does GM Infinite have in Bengaluru?
- 5 are tracked here, across 1 locality including Electronic City. Each has its own page, and its own full report with the filed schedule, unit mix, land schedule and unsold-inventory trend.
Track-record figures are computed from GM Infinite’s own Karnataka RERA filings, merged across the promoter’s SPVs and alias spellings.