Overview
Assetz Canvas & Cove 2.0 - Block A
Part ofAssetz Canvas & Cove 2.02 phases, 617 flats
Overview
Part ofAssetz Canvas & Cove 2.02 phases, 617 flats
Overview
Part ofAssetz Canvas & Cove 2.02 phases, 617 flats

| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 3 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
Part of the full report. Unlock all 4 sections
| Akruti ArkLapsed · completion date passed | Akruti Homes Bangalore Private Limited | Apartment | – | Jul 2024 |
| Arun ConstructionsCompleted (regulator flag) | ARUN CONSTRUCTIONS | Apartment | 854 sqft carpet (as filed) | Completed |
| Assetz Canvas & Cove - Phase 1 Wing A & BActive · 100% built | APG HABITAT PRIVATE LIMITED | Apartment | 266–820 sqft carpet (as filed) | Apr 2027 |
| Assetz Canvas & Cove 2.0 – Block B & CActive · 74% built | APG HABITAT PRIVATE LIMITED | Apartment | 277–1,141 sqft carpet (as filed) | Oct 2028 |
| Aswani SunshineLapsed · completion date passed | Aswani Properties India Pvt Ltd | Apartment | 377 sqft carpet (as filed) | Jul 2019 |
| Blossom ParkCompleted (regulator flag) | Elita Enterprises LLP |
Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 58 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Satellite map with the 2 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 2 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Valuation |
|---|
| – |
| – |
| – |
| Locked |
| Location & risks | – | 1 | 1 | Review |
|---|
| Construction & progress | – | – | 1 | Clear |
|---|
| Developer & finance |
|---|
| Developer | – | 1 | 1 | Review |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Plot |
| ~1,200 sqft (estimate: filed carpet plus 25%) |
| Completed |
| BrindavanLapsed · completion date passed | Sri Krishna Group | Apartment | 575 sqft carpet (as filed) | Dec 2024 |
| Calvin Royal ResidencyFiled as completed · no completion certificate on record | R. Krupaker Reddy | Apartment | 745 sqft carpet (as filed) | Aug 2018 |
8 of 64 other projects in Hosur Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Assetz Canvas & Cove 2.0 - Block A in the interactive atlas
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
| Building plan (BBMP) | Sanctioned 6 Jun 2024 · No. BBMP/Addl.Dir/JDSOUTH/0077/23-24 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire NOC | KSFES/NOC/356/2022 · issued 10 Nov 2022 | Clear |
| Environmental clearance | SEIAA 107 CON 2022 · EC identification no. EC23B000KA111483 · issued 15 Feb 2023 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water and sewerage NOC (BWSSB) | issued 24 May 2023 |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 30 Apr 2029 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 133/1, 134/3 | Converted 31 Oct 2008 · Deputy Commissioner Bangalore | |
| Sy 134/1 | Converted 31 Oct 2018 · Deputy Commissioner Bangalore | |
| Survey numbers | 133/1 · 134/3 · 134/1 |
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Map of the ground within about 450 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main) | Clear |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 620 m, SUBASH NAGARA | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | 30 m to the south-east, secondary drain | |
|---|---|---|
| Nearest lake, tank or pond | 100 m to the south, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | Review |
| Electricity, built | 0% | |
| Outdoor Sports facility, built | 0% | |
| Swimming Pool, built | 0% | |
| Parks, built | 0% | |
| Water and Sanitation, built | 0% | |
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.25 (305 covered spaces for 244 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
As the promoter reported it

| Main structure | 18% · planned by 27 Apr 2027 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 27 Sep 2028 | |
| Internal roads | Not verified yet | |
| Club house | Not started | |
| Completion | 65% | |
| Completion, accountant | 63% of the estimated cost spent | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 30 Apr 2029 | |
| RERA completion date | 30 Apr 2029 | |
| Work began, as filed | 1 Jul 2024 | |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 87.53 m filed | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Provided | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Mar 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | KSFES/NOC/356/2022 · issued 10 Nov 2022 | |
| Environmental clearance | SEIAA 107 CON 2022 · EC identification no. EC23B000KA111483 · issued 15 Feb 2023 | |
| Architect, quarterly | Form 5 · Mar 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 12 Jun 2024 · site inspected 11 Jun 2024 | |
| Engineer's certificate, registration | Dated 12 Jun 2024 | |
| Chartered accountant's certificate, registration | Dated 8 Jul 2024 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹54.38 Cr 26.6%Development · ₹149.99 Cr 73.4%
| Estimated cost | ₹204.37 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹117.66 Cr | |
| Estimated cost, Form 4 Q1 2026-27 | ₹255.66 Cr | |
| Cost incurred | ₹161.03 Cr (63% of the estimate) | |
| Cost left | ₹94.64 Cr | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
Sold (238) 97.5%Unsold (6) 2.5%
| Sold, Q3 2025-26 | 195 / 244 · 49 available | |
|---|---|---|
| Sold, Q4 2025-26 | 231 / 244 · 13 available | |
| Sold, Q1 2026-27 | 236 / 244 · 8 available | |
| Sold, Q2 2026-27 | 238 / 244 · 6 available | |
| Unsold, Q2 2026-27 | 6 | |
| Sold in Q4 2025-26 | 36 | |
| Sold in Q1 2026-27 | 5 | |
| Sold in Q2 2026-27 | 2 |
| Escrow bank | HDFC · Richmond Road | |
|---|---|---|
| Designated account, collected | ₹28.08 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹16.82 Cr in Q2 2026-27 (60% of that quarter's deposits) | |
| Net amount withdrawable, Form 4 | ₹31,18,17,682 | |
| Withdrawn from the escrow account to date | ₹1,29,84,57,977 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan | Sundaram Alternate Assets Limited · ₹120.00 Cr disbursed | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan (BBMP) | Sanctioned 6 Jun 2024 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | HDFC · Richmond Road | |

Map of storm drains, lakes and government-flagged flood locations within about 450 m of the site.
Ten-year July mean for this taluk: 23.2 m
Across Bengaluru South, the water table sat 16.9 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 23.2 m, and it fell 4.2 m over the year.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 16.9 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | BWSSB | |
| Nearest city water main | 80 m | |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | 30 m to the south-east, secondary drain | |
| Ground level | Not verified yet | |
| Metro, operational | 1.7 km, Singasnadra | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 37.4 |
| MG Road (CBD) | 12.3 |
| Manyata Tech Park | 19.5 |
| ITPL, Whitefield | 17.0 |
| Ecospace, Bellandur ORR | 8.0 |
| Electronic City Ph 1 | 5.8 |
| Landfill or waste transfer station | 2.1 km to the south-east | |
|---|---|---|
| Sewage treatment plant | 1.6 km to the north, named Chikkabeguru Sewage Treatment Plant on OpenStreetMap | |
| Quarry | 1.3 km to the south | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 1.3 km to the west |